The Project
Estimated Completion Date: February 2028
Project Participants:
- Owner: SPX and SANCA
- Project Management: EQC Engenharia
- General Contractor: SANCA
This development consists of a logistics warehouse complex. The extended construction schedule is primarily due to the need for a preloading embankment process, requiring a minimum duration of six months to achieve adequate soil consolidation before construction activities can proceed.
Project Information
- 4900 Nações Unidas Avenue, Bonfim District, Osasco – SP, Brazil
- Industrial & Logistics
- Owner-Occupied
- Total Area: 20,205.87 m²